Working on behalf of CNL, Golder and Associates is conducting utility locates and borehole drilling/soil sampling within municipal road allowances, right-of-ways and laneways throughout Port Hope.

Road_Allowance_C2_Sites

    Anticipated schedule for August 2017

    August 01 - Unopened road south of Shuter Street
    August 02 - Oliver’s Lane
    August 03 - Laneway off Sherbourne Street
    August 04 - Laneway off Strachan Street
    August 04 - Laneway off Little Hope Street

    Fast facts about the road allowance testing

    • No road closings are anticipated.
    • The work is expected to take approximately six months.
    • Approximately 160 road allowances, alleys and laneways will be investigated; all other road allowances were surveyed in 2001.
    • Results from this testing will determine which road allowances will require a cleanup for low-level radioactive waste, expected to begin in 2018.
    • This work is being done as part of the Property Radiological Survey

     

    For more information, contact the PHAI at:
    115 Toronto Road, Port Hope, ON L1A 3S4 • 905.885.0291 • phai.ca