Welcome Waste Management Facility

LTWMF
  • 450,000 m3 of historic LLRW

Remediation/Restoration Plans

  • Waste has been excavated from areas east and north of the existing waste burial area to
    allow the onsite infrastructure (roads and support structures) and the base of the first
    cell (Cell 1) to be constructed. The excavated waste is temporarily stockpiled at
    the western end of the existing waste burial area
  • Excavated waste will be placed into the mound
March 29, 2018