Pine Street North Consolidation Site – Currently under remediation

Waste from various Port Hope sites temporarily stored in a containment mound at this site is currently being excavated and transported to the LTWMF via the trucking route that exits on to Cavan Street. This work is expected to be completed by spring 2022.

In order to facilitate the cleanup of the sites as well as to accommodate the volume of truck traffic, the internal haul road was upgraded. In addition, early works included the construction of a new site access road (from Pine Street) and a laydown area for site trailers and worker parking. These upgrades will remain in place throughout the duration of the remediation work in the Highland Drive area, after which they will be removed and the area reinstated to pre-construction conditions.